Freedom Village- Residential Duplexes

Description

Wayne County partnered with Wayne Metropolitan Community Action Agency (WMCAA), Samaritas and the city of Hamtramck as part of Freedom Village, a resettlement program designed to provide refugees and immigrants with transitional affordable housing. This was Funded with federal housing dollars, construction of three two-family homes in the City of Hamtramck. Freedom Village seeks to provide a better life to low-income refugees and immigrants by surrounding them with the resources they need to eventually pursue permanent homeownership opportunities. The purpose of Freedom village project is to develop new-construction affordable housing on Wayne County Land Bank-owned parcels in the City of Hamtramck, with Wayne County Metropolitan Community Action Agency serving as the property developer and owner and Samaritas serving as the refugee placement and services provider.

DMC Consultants, Inc. was contracted by Wayne Metropolitan Community Action Agency (WMCAA) to provide General Construction services to construct new 6 duplex units in 3 buildings for Freedom Village. These units to be built on vacant lots located 2412-2430 Faber Street, Hamtramck, Michigan.

Project Name Freedom Village- Residential Duplexes
DMC’s Role General Contractor/Construction Manager
Client Wayne Metropolitan Community Action Agency (WMCAA)
Architect Stevene C.Flums, Inc.
Status August 27, 2019 – October 30, 2020

Scope Of Work

The scope of services included building 3 Two Family Duplexes. The key activities included  Site Clearing, Excavation, Site Utilities, Foundation and Concrete, Rough and Finish Carpentry, Electrical, Mechanical, Plumbing, Insulation, Roofing, Landscaping and Play Structures. The scope also included right-of-way permit and traffic engineering during the duration of the project.

        DMC finished the project on Schedule and Budget.

The Trade’s includes

  • Site work
  • Excavation
  • Concrete
  • Roofing
  • Carpentry
  • Mechanical, Electrical, Plumbing
  • Landscaping
  • Permitting

        DMC finished the project on Schedule and Budget.

X